Mexus expects the returns to stabilise in the next few days allowing for the gold extraction process to begin. The loading of an additional 5000 t of mineralised material on pad #2 will be completed by the end of the week.

The leaching of pad #2 will commence once returns from pad #1 peak. The company will have continuous flow from approximately 10 000 t of material on pads 1 and 2 with grades expected to reach 4.5 g/t gold.

The mining of an additional 5000 t of mineralised material has already begun and will be ready to place on pad #1 when leaching moves to pad #2.