Downer was awarded the contract based  on  its  price  competitiveness,  relevant  experience  on  technically  similar  projects,  and  demonstrated  leadership  in  safety, environmental  stewardship  and community engagement.

 

The cost of the mining services contract was in line with the cost estimated in the Gruyere feasibility study.

Gruyere JV General Manager Operations, Steve Price, said: “The award of the mining contract is the result of six months work that involved numerous capable contract mining companies.  Downer was selected as the preferred Business Partner for the Project as they led in all facets of the key criteria set for the award of the mining contract.  We are looking forward to Downer joining the Gruyere team as a key Business Partner and contributing to the future success of the project.“

 

Downer will have a workforce of approximately 170 personnel engaged in the project and will commence construction of the mining infrastructure (workshops and office buildings) in the March 2018 quarter.

    

Mining activities are scheduled to commence in the December 2018 quarter using a fleet of 225 t payload dump  trucks,  400 t  excavators,  production  blasthole  drills  and  support  equipment  to  move  around  31  million tpy of material.