For the time being, the longwall is at the commissioning stage, but the target daily progress is planned to be in the range of 8.2 m, with the daily output of 3000 t of coal.
The longwall shearer comprising: the GH9-38/VE plough, JZR-11/25 mechanised roof support sections and PF4/932 face conveyor, supports operation of seams with the thickness from 1 - 1.7 m. The plough head may have a cut of as much as 21 cm, working at the speed of 1.9 mps. Such fast daily progress of the longwall front requires efficient preparation of longwall roadways.
A plough longwall is nearly fully automated and controlled using the control panel located in the longwall roadway. The longwall’s staffing is limited to the absolute minimum and amounts to 3 - 4 miners.
In a longwall mined in the traditional way 12 people have to be employed. Unfortunately a plough has its drawbacks. With such a fast progress, more miners in the longwall bays are required. The mining of the PW-1 longwall is planned to be closed by mid-March 2020.
After we finish to mine the PW-1 longwall we plan to use the plough complex in further four longwalls with low seams,” said Malcharek.